All Collections
LB Geniebelt - Multi-project Planning
Project Features
LB Geniebelt - How to use the baseline feature?
LB Geniebelt - How to use the baseline feature?
Paul Etienne avatar
Written by Paul Etienne
Updated over a week ago

Use our Baseline feature to easily see which tasks have shifted position and/or duration.

To create a baseline, select the Gantt Options Icon within the Toolbar and choose Show Baseline and then Create a Baseline. Then you simply name it. By default we provide the date and time of creation.

Creating a Baseline will mark the location and duration of every task within the project with a Yellow Line.

Then at any point in time you can select that baseline and the yellow lines marked at that time will be shown so you can easily see which tasks have moved or changed duration.

Currently, Baselines are not included in the Print Gantt function.

When you import or reimport a program, we automatically create a baseline.

Did this answer your question?