Everyone can update or comment on a task, except for Observers.

Here are the things you can do on a task:

  • Update the Progress Percentage

  • Report a Problem

  • Attach an Image or File

  • Leave a Comment

  • Mention @ someone so they get notified

It is very simple to update the status or comment. Whether on Desktop or the Mobile App, to update the status, take a photo or report a problem, you first need to select the task and then click on the submit update button.

Mobile

  1. Select the task.

  2. Update the percentage, write a comment, report a problem and/or add an attachment/photo.

  3. Click Submit

Desktop

1.On the Gantt Chart, select the Task. In the right hand side panel, then click on the LB Geniebelt icon next in the Status section or simply click on the Progress Bar.

2. Once open, you can update the percent or custom unit, write a comment, report a problem and/or add an attachment/photo. Click Update progress.


Please note: if you want to just leave a comment, you don't need to submit an update. On each task there is a comment field, where you can write your note or mention someone.

Any information added will be recorded and tracked within the audit trail.

Any status update or comment will also create a beat notification for the admin users and any member assigned to the task.